What they mean
- ETD: Estimated Time of Departure.
- ETA: Estimated Time of Arrival.
- ATD and ATA: Actual Time of Departure and Arrival, that is, the moments when departure and arrival really took place.
They are used for ships, aircraft, trains and trucks. In sea and air transport they appear on booking confirmations, on loading plans and in tracking systems.
Why they change
"Estimated" means estimated. The typical causes of change are:
- weather and sea conditions, or road traffic;
- congestion at ports, terminals and airports, with waits for berthing or unloading;
- delays on earlier voyages: a ship that leaves one port late arrives late at the next;
- operational decisions by the carrier, such as skipping a call (blank sailing) or changing the order of ports;
- strikes, inspections or border closures.
For this reason, in a contract of carriage the ETD and ETA dates are almost never a promise by the carrier: the conditions of carriage normally state that they are indicative.
Why they matter
- For pick-up and the cut-off: the date for delivering the goods to the terminal is calculated from the ETD.
- For customs formalities: the expected arrival is the reference for preparing the declaration and the advance arrival notices; for those, the updated ETA is essential.
- For delivery: the buyer organises collection, warehouse and staff around the ETA.
- For demurrage costs: the days of container free time start from the actual arrival, not from the estimated date; exceeding them leads to demurrage and detention.
- For contractual deadlines, such as the latest shipment date of a letter of credit.
Practical example
A container for North America has an ETD of the 10th and an ETA of the 28th of the month. On the 8th the carrier reports that the ship is late and moves the ETD to the 12th: the ETA slips accordingly. The customer cannot count on the 28th to organise the warehouse, and the freight forwarder updates the dates for delivery at destination and for customs notices. If the ATA is the 30th, the days of free time start from that date.
Dalè passes on to the customer the dates given by the carrier and updates them when they change, and reminds you not to set rigid deadlines on estimated dates alone.
Common mistakes
- Treating the ETA as a guaranteed delivery date.
- Not checking for updates in the days before loading.
- Confusing the ETA at the port with delivery to the customer's warehouse, which comes after unloading and customs clearance.
- Calculating free time from the estimated date instead of from the actual arrival.