What detention is
The container belongs to the shipowner, or to a leasing company. Whoever collects it uses it for a limited period: the time allowed at no cost is the free time. If it is kept beyond that, the carrier loses the chance to reuse it and charges a daily sum. That sum is detention.
When it starts
- On import: from the collection of the full container from the terminal until the empty is returned to the depot indicated.
- On export: from the collection of the empty container at the depot until delivery to the terminal already loaded.
Common causes: slow unloading at the company, closed warehouse, no vehicles to take the empty back, empty depot full or closed, queues at the terminal, seals or customs checks that lengthen the time.
Difference from demurrage
The difference is where the container is. Demurrage: in the port, beyond the time allowed. Detention: outside the port, beyond the time allowed. In one shipment one can start first and then the other. Some carriers offer a combined free time, which runs from entry into the terminal until the empty is returned. The conditions are written on the quotation and on the carrier's website: they must be read before booking.
A practical example
A company in the Brescia area receives a container of raw materials from a port in Northern Europe. The container leaves the terminal and arrives at the plant, but unloading is put off for a few days for lack of staff. Then the empty depot indicated by the carrier has long queues. The free time ends and detention begins. If the company had communicated the unloading date in advance, the booking of the collection and of the empty return would have been aligned. Dalè coordinates transport, collection and return with the customer to avoid downtime.
How to reduce it
- Ask for the free time for each phase and the rule on public holidays.
- Plan unloading before arrival: staff, vehicles, space.
- State the return depot and check its hours and opening days.
- If the delay is not the customer's fault (terminal closed, depot full, strike), document it straight away and ask for an extension.
- For loads that take time, such as plant to be assembled, consider buying additional days in advance.
Regulatory framework
There is no uniform international rule: the carrier's conditions of carriage and the applicable law apply. For shipments to and from the United States, the Federal Maritime Commission has introduced, with part 541 of title 46 of the CFR, requirements on the content of invoices and a 30-day deadline for issuing them. A section of the rule on the billable party was vacated in 2025: it is therefore worth checking the text currently in force. Elsewhere the contractual clauses apply.
More on the container cycle in the container guide; on the practical management of transport, FCL containers. The terminal cost is explained under THC.
Sources
A shipment to organise?
Tell us what you are shipping and where to: we reply with the route, the documents required and a quote.
Related Dalè services
Related glossary terms