What demurrage is
The word generally refers to the delay of a ship or a cargo that stays put beyond the planned time. In container transport it has a practical meaning: the container is taking up space in the terminal, and after a certain number of free days a storage charge is paid. The free days are the free time. After that, each day has an amount, often rising in steps.
When it starts
- On import: from the day the container is unloaded until it leaves the terminal. If the goods are not cleared, or a document is missing, the container stays where it is.
- On export: from the day the full container enters the terminal until loading, if it is delivered well ahead of the opening of loading operations.
Typical causes: bill of lading not released, payment of freight or destination costs not completed, customs waiting for documents, physical or health inspections, strikes and port congestion, pick-up not organised for lack of vehicles.
Difference from detention
Demurrage and detention are often confused, but they concern two different moments. Demurrage is storage inside the terminal. Detention is the use of the container outside the terminal beyond the time allowed: it starts when the container, once collected, is not returned empty within the days provided. In some contracts the two items are merged into a single combined free time, and the conditions must be read case by case.
A practical example
A company in Brescia imports a container of components from China. The ship arrives at Genoa, but the customs declaration is not ready because a certificate required for import is missing. The free days pass and the container stays in the yard: demurrage starts. If the customs department had received the documents before arrival, it could have lodged the declaration while the ship was still at sea. Dalè prepares the customs documentation in advance for exactly this reason, in its own department in Brescia.
How to reduce the risk
- Ask the shipowner, already at booking, how many free days are included and whether they are working days or calendar days.
- Prepare invoice, packing list, certificates and the original or surrendered bill of lading (telex release) in advance.
- Book the road transport before the ship arrives.
- Check the actual arrival date and compare it with the expected one, because the free time runs from discharge.
- Dispute in writing any charges that are not consistent with the conditions, with evidence of delays not attributable to the customer.
For shipments to and from the United States there are specific billing rules: for example, the Federal Maritime Commission has set out in part 541 of title 46 of the CFR the timing and minimum content of demurrage and detention invoices, including the 30-day deadline for issuing them. For other countries the shipowner's conditions and local rules apply.
More information on the container's journey is on the FCL containers page and in the container guide.