Two linked concepts
- Heavy lift: a single heavy piece of cargo that needs high-capacity cranes, equipped ships or special lifting systems. There is no single weight that separates normal cargo from heavy cargo: it depends on the ports, ships and equipment used.
- Project cargo: a complex supply made up of many pieces of different sizes and weights, destined for a project, for example a production plant, a wind farm or an infrastructure work. It includes coordination of several transports, staggered deliveries and documents.
Many pieces of project cargo are abnormal loads on the road leg, and general cargo or wheeled cargo on the sea leg.
How it is planned
- Cargo data: weight, dimensions, centre of gravity, lifting and securing points, technical drawings.
- Route survey: from the place of departure to the port, by land and by sea, checking bridges, tunnels, quays and crane capacity.
- Choice of ship: a heavy-lift ship with its own cranes, a multipurpose ship, or a Ro-Ro for wheeled pieces, or special containers (flat rack, open top) when the dimensions allow.
- Securing plan: calculation of the lashing and support system, to be agreed with the master. See also cargo securing and stowage.
- Authorisations: permits for abnormal loads, port access and customs documents.
Contracts, freight and insurance
In project cargo, voyage charters are often used with special terms for loading and discharging, such as the FIO clauses, and delivery plans in several shipments. The cost of freight depends on the characteristics of the cargo and the route; it is a tailored negotiation, not a standard rate. For valuable and delicate cargo it is important to have suitable cargo insurance, with an assessment of the risks of lifting and of carriage on deck; on this subject see also deck cargo.
A practical example
A manufacturer of industrial plant in Lombardy has to deliver a production line to a Gulf country. The supply includes steel modules, some too bulky for a container. The lighter modules travel in containers, the large ones on a general cargo ship with cranes. The forwarder coordinates abnormal road transports to the port, bookings, documents and the handling of shipments in several lots, so that the goods reach the site in the order required by the assembly.
Common mistakes
- Weight and centre-of-gravity data that have not been verified, forcing the lifting plan to be redone.
- Not checking the limits of the quay and cranes at the port of destination.
- Lack of coordination between deliveries: if one piece arrives late, the whole assembly can stop.
- Packing not suited to lifting with straps or hooks.
Dalè, from its base in Brescia, can handle the coordination and customs formalities of these transports by sea and by road; for loads of this kind it is best to contact us beforehand, already at the stage of the offer to the end customer, through the quotation form.
Sources
A shipment to organise?
Tell us what you are shipping and where to: we reply with the route, the documents required and a quote.
Related Dalè services
Related glossary terms