What counts as delay
Goods are late when they are not delivered within the agreed deadline. If no deadline was agreed, what counts is the time that can reasonably be expected of a diligent carrier, taking the circumstances into account. It is best to set the deadline in writing: without one, delay is harder to prove.
It should not be confused with loss: if delivery is delayed beyond very long limits, the goods may be treated as lost. Under the CMR the presumption arises 30 days after the agreed deadline or, if there is no deadline, 60 days after the goods were taken over (Art. 20): the person entitled may then consider the goods lost.
The rules by mode
- Road (CMR): the carrier is liable for damage caused by delay (Arts. 17 and 19). Compensation cannot exceed the carriage charges (Art. 23, para. 5), unless a special interest in delivery has been declared (Art. 26). The written claim must be made within 21 days of the goods being placed at the disposal of the consignee (Art. 30). The action is time-barred after one year (Art. 32).
- Air (Montreal Convention): the carrier is liable for damage caused by delay (Art. 19) if it does not prove that it took all reasonable measures to avoid it. The claim must be made within 21 days of the goods being placed at disposal (Art. 31); the lawsuit within two years.
- Sea: the Hague-Visby Rules do not expressly regulate delay: what counts are the contract, the bill of lading and national law.
- Domestic transport: the Civil Code and the special laws on road haulage apply, together with the terms of the contract.
Damage from delay must be proved
Delay alone does not entitle you to a sum. Whoever claims must show that they suffered damage and that it results from the delay. Typical losses are: production downtime, a penalty paid to the customer, storage costs, the loss of a season or a trade fair, spoiled goods. The Incoterms® chosen also matter: with a term that places risk and responsibility on the buyer, the seller does not always have standing to sue; the sales contract may in any case provide for penalty clauses for delay.
What to do as soon as the goods are late
- If the deadline is of the essence (goods for a trade fair, components for a production line), say so in writing and ask for a recovery plan, for example another vehicle or another flight.
- Receive the goods, without refusing them just because they are late, and note the actual date on the delivery document.
- Send the written claim, by certified email (PEC) or registered letter, within the time limit, citing the shipment, the expected date and the actual date.
- Gather evidence of the damage: invoices, penalties, emails with the customer. Many cargo policies exclude delay: it is worth checking.
Practical example
A company from Brescia ships a load of components by road to France, to be delivered by a specific day. The truck arrives late, the customer's line stops and the customer applies a penalty. The company writes to the carrier within 21 days of delivery. But compensation under the CMR does not exceed the freight charge, unless a special interest in delivery was declared beforehand. When punctuality is critical, it is worth declaring it and agreeing a written deadline. For road see land transport.
Common mistakes
Not setting any deadline, not noting the delivery date, writing to the carrier too late, asking for the value of goods that arrived intact.