What it is
When stock is managed continuously, the stock level is checked after every movement and, as soon as it falls to the reorder point, the order is issued. Between issuing the order and the arrival of the goods a period passes, called the lead time: during that time consumption continues. The reorder point is calculated precisely to cover that consumption.
The formula
reorder point = average consumption per period × lead time + safety stock
Consumption and lead time must be expressed in the same unit, for example pieces per day and days. The safety stock is added to absorb fluctuations in consumption and delays.
Worked example
An item is consumed on average at thirty pieces a day. The supplier delivers ten days after the order, and a safety stock of one hundred pieces is decided.
- consumption during delivery: 30 × 10 = 300 pieces;
- reorder point: 300 + 100 = 400 pieces.
When stock falls to four hundred pieces, the order goes out. If all goes as planned, the goods arrive when about one hundred pieces remain, which is exactly the safety stock.
And the quantity to order?
The reorder point says when to order, not how much. For the quantity two approaches can be used:
- fixed quantity: the same lot is always ordered, chosen on the basis of ordering costs, holding costs and the supplier's minimum;
- periodic review: stock is checked at regular intervals (every week, every month) and you order what is needed to return to a target level.
The first system reacts better to irregular consumption; the second simplifies purchasing when suppliers deliver on a fixed calendar.
When the supplier is far away
For supplies from abroad the lead time includes not only production and transport, but also customs and any wait for loading. Fixed days should also be considered in good time: holidays in the countries of origin and plant closures. Dalè, with its customs department, helps estimate which steps are expected from pick-up to delivery in Brescia, so that the lead time entered in the system is realistic and not optimistic.
Common mistakes
- Using the lead time "promised" by the supplier instead of the real one, measured on the latest deliveries.
- Not updating average consumption when demand changes (seasonality, promotions).
- Calculating the point on physical stock without considering what is already committed to customer orders.
- Forgetting orders already on their way: also count goods ordered and not yet received, so as not to order twice.